Dumpsters for Large Construction or Demolition Jobs

There are many things to consider before renting roll-off dumpsters for large construction or demolition projects. Among the key considerations include the kind of material(s), duration of the project, the volume of debris, availability of the rental provider’s container stock and a lot more. Proper planning can easily minimize dumpster rental costs during a huge project by 20% or more.

A 10 yard dumpster usually costs $304. A 20 yard dumpster costs $383 and a 30 yard dumpster costs $441. A 40 yard dumpster costs $488. Ask the dumpster rental company if they provide contractor’s pricing, or if they provide discounts for renting multiple dumpsters. It is likely that a local hauler is going to be willing to work out a deal with a contractor willing to rent multiple dumpsters on a continual basis.

It is usually more cost-effective to rent the largest dumpster(s) available that is going to work with the kind of debris your site is generating. If going with the bigger dumpster saves you from having to rent a second, third, etc. dumpster, that’s several hundred dollars you are going to save on costs of disposal. Get a Quote Today at: calldumpsterman.com

A precise estimate is very important in minimizing disposal costs. A basic formula utilized by FEMA could help you estimate the debris created in a demolition project. For a building demo, the formula is Length x Width x Height x 0.33/27 = Cubic yards of debris. For a single-family home demo the formula is Length x Width x S(number of stories) x 0.20 x VCM (vegetative cover multiplier) = cubic yards of debris, where vegetative cover multiplier = yard waste.

One ton of construction and demolition (C&D) debris equals approximately 2 cubic yards. As soon as you have your debris estimate, it is a lot easier and more accurate to determine the roll-off dumpster requirements. For the biggest jobs, like industrial buildings, the use of a 50 cubic yard or larger dumpster/trailer could be a good option.

A lot of dumpster rental companies do not have this bigger dumpster option, so 40 yard containers are usually the highest capacity offering in many areas. When clean-loading heavy debris, like shingles or concrete, a 40+ yard dumpster is generally not required. This kind of high-density, low-volume debris is best disposed of in smaller containers like 10 or 20 yarders. In fact, many rental companies require the use of smaller containers for heavy materials.

When it comes to the disposal of debris, proper planning and strategy are important to maintaining a smooth workflow at a demolition or construction site. As already mentioned, the whole cost of debris disposal is hugely affected through planning efficiently, but a sound debris removal strategy is also beneficial in many ways.

You need to consider improved worksite efficiency. With the right planning, you can minimize or eliminate delays related to dumpster delivery, swap-outs and pick-ups. It is important to be clear with the dumpster rental company on your disposal schedule and needs. If they cannot meet those needs, you have to find another rental provider. By disposing of debris right away in dumpsters instead of piling it up, you can maintain a safer work site. The fatal injury rate in the construction industry is higher than the national average for all jobs, according to OSHA. As a contractor, make maintaining a clean, safe job site a priority.

You also need to know the needs of the job. This means that contractors have to estimate the number of total dumpsters needed to finish the job, as well as whether container swap-outs or live-loading is a part of the debris removal strategy. If it is, verify with the dumpster rental company that they can meet those demands before you book the dumpsters. Not all the rental companies could accommodate live-loading scenarios or other unique circumstances. They may simply not have the equipment or resources for delivering multiple dumpsters at once in the day.

There are some other tips so you can save on dumpster rental costs for bigger projects. You can work out a deal with a dumpster rental company you plan to use on a regular basis. If you provide lots of business for them, they will most likely be willing to offer special contractor’s pricing.